Status 2026-10-28: being built; all nine decisions are taken (table at the end), and the state of each step is in implementation-plan.md. The findings come from reading edakit at a8b6011 (with PRs

78 and #79) and the repositories of the reference project and the Christmas bell.

Goal

Every edakit project gets a text file that says what the circuit must do – each requirement with an ID and a criterion to test it by. An agent leads there: it asks until a vague idea has become a sentence that can be tested, and the user approves it.

Two questions show whether the goal is reached:

  1. What should the circuits of the reference project's tree and of the Christmas bell do? The answer is in one file per project, not spread over READMEs, decisions and chats. What firmware and mechanics must do stays in the projects' own documents (decision 3).
  2. Does the circuit do it, and how do we know? Every requirement points to its evidence – simulation, check or measurement – and edakit shows which ones have none yet.

It complements the concept design-as-text.md: that one is about the circuit being text, this one about what the circuit should do.

Where it stands

All three projects state requirements, but scattered, mostly without an ID and almost never with a pointer to their evidence. Exactly two are traceable today: FW-4 and FW-5 of the reference project.

Where What it says ID Evidence linked
edakit, skill circuit-design §1 asks for supply, inputs and outputs, quantity, enclosure, purpose and "what matters to the user" – partly: purpose goes into the graph, the touch limit into touch_c (E-2), a budget into [cost] budget; the rest stays in the report in the chat
edakit, skill decision-round "… is a must" counts as a hard requirement D-… as a decision, not as a requirement
edakit, acceptance M-4 test steps after delivery M-4 names parts and functions, not requirements
bell, README.md and docs/IMPLEMENTIERUNG.md Christmas Eve step by step: press start, the bell rings mechanically after 65 s – no
bell, docs/decisions.md requirements inside decisions: power bank (D-8), timer 10 s to 24 h (D-17), "Requirements from the M-1 review" (D-13) D-… partly: D-8 as i_min_a 0.1 A in sim.json (E-3)
reference project, docs/schaltungsbeschreibung.md "Daraus ergeben sich die Anforderungen an die Schaltung" (the requirements for the circuit): six points, e.g. 0.5 A from a USB 2.0 port – indirectly: usb_i_max_a 0.5 in the simulation, whose note points to usb_baum.md
reference project, docs/kalender.md constraints and the behaviour of every element of the tree – no
reference project, firmware/ANFORDERUNGEN.md FW-4 buzzer never high permanently, FW-5 defined start; FW-1 to FW-3 kept as dropped FW-… yes: the rule watcher simulator/regeln.py
reference project, hardware/release/abnahme.md acceptance steps with target values from the simulation 1.1 … to decisions and checks, not to requirements

FW-4 and FW-5 are the pattern in small: an ID, one testable sentence, the reason, the test – and a dropped requirement stays with its reason. This concept extends it to everything the circuit should do.

The gap

There is no place where every requirement stands with an ID, and from there a pointer to its evidence. The consequences show in both projects already:

  • The answer takes six files. What the tree should do is in kalender.md, baum_tage.md, schaltungsbeschreibung.md, hardware.md (D-1 to D-48), usb_baum.md and ANFORDERUNGEN.md.
  • Contradictions stay. The bell's README and IMPLEMENTIERUNG.md say "Servo separat (5V, 1A)" (a supply of its own for the servo), D-3 puts the servo on the Nano's 5V pin. In the reference project, firmware_test.md ("Mit vollen Zellen schaltet der Baum nie ab": with full cells the tree never switches off) contradicted decision D-38; only a risk review found it.
  • The acceptance test checks parts, not requirements. The bell's M-4 asks for "the servo swings". Whether the bell runs on a power bank (D-8), it does not test.
  • Requirements hide in decisions. D-13 holds "Requirements from the M-1 review" for the ESP32 firmware. The firmware cites D-13 in a comment; no test checks it.
  • Collected and lost. circuit-design asks for the requirements in a decision round. Only a few find a home: purpose in the graph, the touch limit in touch_c (E-2), a budget in [cost] budget (skill new-project). The rest is in the report and goes with the chat.

So the gate knows no requirements: a changed requirement voids no sign-off, and no check reports a requirement without evidence.

Proposal: the requirements file

Every project gets hardware/requirements.toml, named in edakit.toml under [project] requirements. The file describes the circuit: what the boards must do and withstand, each requirement with its evidence. What firmware and mechanics must do stays in the project's own documents, such as the tree's firmware/ANFORDERUNGEN.md (decision 3).

It has two levels, along the gap between wish and circuit:

Level ID Content Evidence
need N-1 … what someone wants, in their words: who, in which situation, what for through the requirements that follow from it
requirement R-1 … one testable sentence with quantity, limit and condition; binding as must, should or may check, simulation, sign-off, acceptance or project script
[[need]]
id = "N-2"
text = "The bell runs from a USB port or a power bank."
who = "parents"
source = "graph.json purpose, D-8"
status = "accepted"

[[requirement]]
id = "R-4"
text = "In operation the circuit draws 100 to 500 mA from USB, in every state of countdown and ringing."
from = ["N-2", "D-3", "D-8"]
binding = "must"
verify = [{ rows = "E-3 * U1 *" },
          { accept = "on a power bank: press start, the bell rings" }]
status = "accepted"
  • One sentence, one statement. Numbers come with unit and condition. Words like "loud", "reliable" or "inconspicuous" the agent turns into numbers by asking.
  • from says where it comes from: a need, a decision, a standard (USB 2.0: 500 mA) or a sign-off (the radio conditions of M-6).
  • verify says what tests it. rows are rows of the gate protocol, matched as accepted_warnings are ("ID scenario item check"). signoff is a manual check, accept a step of the acceptance test, script a project script of the kind check (concept project-scripts.md).
  • IDs are stable, as in the rule catalog. A dropped requirement stays with its reason (status = "dropped", reason = "D-47: no cells"), like FW-1 to FW-3 of the reference project.
  • The agent drafts, the user approves. Drafts carry draft; only the user sets accepted. Approving a requirement joins the user's real decisions in working agreement 4 (handbook 11.4), next to accepting a warning and money. A change to an accepted requirement is a decision in the decision log.

TOML as for the board and schematic files: readable by people and LLMs, no JSON. Variants read the main project's file and add entries for what only they have.

The agent

The requirements engineer is a new role in two parts, because asking back needs a conversation, and an agent in its own session does not talk to the user.

  • Skill requirements, in the session with the user: collects, asks back in a decision round, writes drafts into the file and has them approved. It writes only requirements.toml and decisions, never the graph.
  • Agent requirements-engineer, in its own context, changes nothing: reads every document of a project and returns candidates with the place it found them, contradictions, vague words and requirements without evidence. It does the first inventory and checks a finished file as a second opinion.

It asks these questions until the idea has become requirements for the circuit; what it learns about firmware or mechanics, it leaves to the project's documents.

Topic Question Example: the bell
people Who uses, builds, gets it? Who must not notice it? parents; children, who should not discover the bell
course How does one use go, step by step? start, the parents leave, it rings after 65 s
surroundings Where does it stand, where does the power come from, how often and how long does it run? a shelf, USB or a power bank, once a year for about 15 min (D-10)
operation What does one press, see, hear? two buttons, five LEDs, the bell
limits What must never happen? a stalled servo does not overload USB permanently (D-3)
frame purpose, quantity, budget, date private (D-16), ready before Christmas Eve
non-goals What is explicitly not wanted? no electronic sound

Four rules keep it honest:

  1. Vague words become numbers. "Loud" becomes a question with a proposal, for instance: audible in the next room with the door open?
  2. Contradictions become questions, never resolved silently – in a decision round, as working agreement 5 has it for every open question. "Servo separat (5V, 1A)" against D-3 is an item of that round.
  3. What it does not know stays open. A draft carries the open question, not an invented number.
  4. Every requirement gets evidence, existing or proposed: a scenario, an acceptance step, an item for a review or a project script.

After that circuit-design reads the file instead of asking in §1 itself. A new function starts with its requirement, and the designer's report says which parts meet which requirement.

Traceability and the gate

edakit reads the file and checks the chain both ways: every need leads to requirements, and every requirement ends in evidence that passes.

flowchart LR
    N["need N-…<br/>in the words of those involved"] --> R["requirement R-…<br/>testable: quantity, limit, condition"]
    F["from<br/>D-…, standard, sign-off"] --> R
    R --> rows["rows<br/>simulation, checks"]
    R --> signoff["signoff<br/>M-1, M-5, M-6"]
    R --> script["script<br/>project script"]
    R --> accept["accept<br/>acceptance step"]
    rows --> G["gate protocol<br/>table of requirements<br/>before the order: must blocks"]
    signoff --> G
    script --> G
    accept --> M4["acceptance list in the protocol<br/>M-4 after delivery"]
verify passes when blocks the release
rows at least one protocol row matches and none failed yes, for must
signoff the manual check is signed for the current hash of its scope (circuit, layout or fab) and names the ID yes, if its phase is export
script the project script passes in the gate yes, for must
accept M-4 is signed; the step is on the protocol's acceptance list no, phase acceptance

What can only be tested at acceptance does not hold up the release. The protocol already has an acceptance list (#42): section 6 lists M-4 under "after delivery", and below it every open datasheet point with when = "acceptance" as an unchecked line. An accept step joins it the same way, with its ID: - [ ] R-4: on a power bank: press start, the bell rings. M-4 works through the list. New in edakit:

  • edakit req lists needs and requirements with status and evidence. edakit req R-4 shows the chain of one requirement.
  • New checks in the catalog: every reference resolves. Every accepted need has a requirement, every requirement evidence. Drafts warn as long as the user has not approved them.
  • A section "Requirements" in the gate protocol: per requirement its evidence and the result. It answers the second question without another file.
  • The file counts in the circuit hash, byte for byte like purpose: [release] hash_ignore does not reach into it, because the reviews read it whole. A changed requirement voids M-1 and M-6, as the new purpose of D-16 voided M-1. In a project with [firmware], the firmware contract shows drift as well, because it carries the circuit hash.
  • The reviewers get the file as a source. The electrical reviewer judges the requirements with signoff = "M-1", the PCB reviewer those with "M-5", the regulatory reviewer those with "M-6". Each names the ID in its result. For the electrical reviewer the file replaces "requirements the firmware relies on", which it reads today.

Trial on the bell and the reference project

The first entries are almost word for word in the existing documents. What is missing is nearly always the pointer to the evidence – even where the evidence has existed for a while.

The Christmas bell

Draft Source today Evidence today Evidence with this concept
N-2 The bell runs from a USB port or a power bank. purpose, D-8 – through R-4
R-4 In operation the circuit draws 100 to 500 mA from USB. D-3, D-8 E-3 in sim.json, not linked rows = "E-3 * U1 *", accept on a power bank
R-5 A stalled servo loads USB for one bell phase at most. D-3 scenario servo-stalled as information; the firmware cites D-3 signoff = "M-1"
R-6 The main board, SMD and THT do not transmit. purpose, M-6 M-6 signoff = "M-6"

N-1 and R-1 to R-3 of the first draft – the bell rings 65 s after start, the countdown runs on five LEDs, the bell is struck mechanically – are firmware and mechanics. They stay in the README and IMPLEMENTIERUNG.md (decision 3), and so do two questions of the first draft: 65 s or 30 to 45 s, and how loud. The question the agent would ask: the servo on a 5 V, 1 A supply of its own (README, IMPLEMENTIERUNG.md) or on the Nano's 5V pin (D-3)? Proposal: D-3 holds, and the two texts are corrected.

The reference project

Draft Source today Evidence today Evidence with this concept
N-1 The recipient enters a code every day, and the tree wakes up one stage further. kalender.md, schaltungsbeschreibung.md – through R-1 to R-3
R-1 0.5 A from a USB 2.0 port is enough in every state. schaltungsbeschreibung.md usb_i_max_a in the simulation; its note points to usb_baum.md rows of the simulation
R-2 Swapped wires do no harm. schaltungsbeschreibung.md the tree's check G-10, acceptance step 2.4 rows, accept
R-3 Nothing lights or hums before the firmware runs. schaltungsbeschreibung.md, FW-5 rule watcher script

R-4 and R-5 of the first draft – the buzzer is never high permanently (FW-4), the progress survives unplugging – are firmware and stay in ANFORDERUNGEN.md and kalender.md. "With full cells the tree never switches off" from firmware_test.md would go in as dropped, with the reason D-47: the USB tree has no cells. The inventory itself is the agent's work: read, return candidates with the place it found them, ask the contradictions as questions.

Scope

  • Only the circuit. What the boards must do and withstand belongs in the file. The codes the tree accepts, the bell's countdown and the fit in the stand stay in the projects' documents (decision 3).
  • edakit checks everything in the file: protocol rows, sign-offs, project scripts of the kind check and acceptance steps. It does not run firmware tests.
  • No silent import. The agent proposes, the user approves; nothing is taken over from documents unasked.
  • No tool for large projects: no ReqIF, no baselines, no access rights. Git is the history, the decision log the reasoning.
  • The documents stay. README, circuit description and calendar go on telling the story. They quote a requirement by its ID, as they quote a value since #71: a value block with the source req:R-4 in a file of [docs] files (handbook 6.6), and G-19 finds a stale quote.

Order

  1. Format, parser and edakit req, tested on the example project led-bar.
  2. Checks, the section "Requirements" and the accept lines in the gate protocol, the file in the circuit hash.
  3. Skill requirements and agent requirements-engineer; circuit-design and the reviewers read the file. The plugin test that lets the reviewer prompts name only catalog IDs learns N- and R-.
  4. req: as a source of the value blocks (G-19).
  5. Trial on the bell after its order: inventory, decision round, file – in the bell's repository, at the user's request. Before the order the file would reopen M-1 and M-6.
  6. The reference project, once it has moved to edakit (after its order, EK-1 of its concept).

Decisions

All taken on 2026-10-28. "Accepted" is the user's yes to the proposal; "decided by Claude" marks a technical point the user left to Claude and then confirmed.

# Decision Taken State
1 Two levels need N-… and requirement R-…; the hyphen tells R-4 from R4, as it tells D-8 from D8 today accepted
2 Place and format hardware/requirements.toml in [project] requirements; variants read the main project's file too decided by Claude: TOML like the board files
3 Scope only the circuit: what the boards must do and withstand; firmware and mechanics stay in the projects' documents the user's choice; the proposal was the whole device
4 Binding must without passing evidence blocks the release, should warns, may informs accepted
5 Required optional until the bell and the reference project have a file; then required, as M-1, M-5 and M-6 are accepted
6 Hash the whole file counts in the circuit hash, byte for byte like purpose; hash_ignore does not reach into it accepted
7 Role skill requirements in the conversation, agent requirements-engineer for the inventory and a second opinion decided by Claude: asking back needs the conversation, reading every document a context of its own
8 Acceptance accept steps join the protocol's acceptance list (section 6, after delivery); M-4 names the IDs it tested decided by Claude: the list exists since #42, a second one would compete with it
9 Trial first on the bell after its order, then on the reference project accepted
10 Drafts a draft only warns: it blocks neither the release nor a commit; errors and blocking start once the user accepts it the user's choice on 2026-10-28, built as a follow-up of step 1.6

Sources

  • edakit at a8b6011: skills circuit-design, decision-round and new-project, agents electrical-reviewer and pcb-reviewer, handbook 6.6 (value blocks, G-19), 8 (8.2 hashes and sign-offs, hash_ignore, the acceptance list, M-4), 11.4 (working agreements) and 14 (roles), gate.py (key_of, state_files, state_hash, REQUIRED, protocol section 6), firmware.py (the contract carries the circuit hash), run.py (E-3, i_min_a), test_plugin.py (IDs in the reviewer prompts).
  • The Christmas bell: README.md, docs/IMPLEMENTIERUNG.md, docs/decisions.md, hardware/graph.json, hardware/sim.json, hardware/signoff.json, src/firmware/buttons.ino, variants/esp32/firmware/test/test_bell_timer/test_main.cpp.
  • The reference project: firmware/ANFORDERUNGEN.md, docs/schaltungsbeschreibung.md, docs/kalender.md, docs/verifikation.md, hardware/release/abnahme.md, hardware/sim/config.json, docs/concepts/erledigt/mvp_risiken.md, docs/concepts/offen/edakit.md.